Delivery, packing & documents
All timings are planning estimates, not guaranteed delivery dates. Final timing depends on product availability, production, documentation, customs, border queues, route, weather and destination requirements. The quotation is the controlling document.
Heavy equipment does not travel like a parcel. This page shows the stages, the realistic times, the exit routes we use — road and sea, with the ports named per order — and the document set that travels with the machine.
What actually takes the time
Quotations fail when “delivery time” means different things to buyer and seller. Below, each stage is separated — production, inland haul, customs, cross-border run — so you can plan a crew start date against it.
| Stage | Typical planning estimate | Notes |
|---|---|---|
| Production / build slot | 15–25 days | Standard configuration from stock can be shorter; cold-weather and high-altitude packages add build time. |
| Factory test & packing | 2–3 days | Pressure and flow test, then export packing with loading photos sent to you before the truck leaves. |
| Works → exit port / crossing | 3–6 days road | Overland to Khorgos or Alashankou for Central Asia; to Shanghai, Ningbo or Qingdao when the order moves by sea. Full-truck-load; oversize units may need a low-bed trailer and a permit. |
| Export clearance | 1–3 days | Documents prepared before the truck arrives at the border, not after. |
| Cross-border run to site | 4–8 days | Kazakhstan, Uzbekistan, Kyrgyzstan. Weather and border queueing are the two variables we cannot control. |
| Realistic total to plan with | 30–45 days (estimate) | From deposit to machine on site. Road transit alone is 7–12 days — production and border time sit either side of it. |
Sea freight (FCL) from Shanghai, Ningbo or Qingdao serves the Gulf, Africa and Southeast Asia — transit depends on the port pair and is quoted per order. Rail (container or flat wagon) is 20–35 days transit (estimate) and usually cheaper for multi-unit orders. Air freight moves spare parts, not machines. All figures in this table are planning estimates, not guaranteed delivery dates: final timing depends on product availability, production, documentation, customs, border queues, route, weather and destination requirements. The quotation is the controlling document.
How a machine is prepared for the road



| Item | Standard |
|---|---|
| Machine protection | Unit on skid / chassis, exposed surfaces wrapped, control panel and gauges protected, hoses coiled and capped |
| Loose items | Spare-parts kit, adapters and tools packed in a labelled crate — packing list item numbers match the crate labels |
| Moisture | Desiccant and VCI film on request for sea or long rail routes |
| Marking | Shipping marks with model, serial number and crate number on every package |
| Photographs | Packing and loading photos sent to the buyer before dispatch |
Works, warehouse and loading — what a shipment looks like
Below: the works floor where machines are staged and tested, the assembly line, a unit being moved out for dispatch, and an export project running overseas. Packing-list samples are issued with every quotation on request.





What travels with the shipment
Commercial and transport
Proforma invoice, commercial invoice, packing list, bill of lading or CMR, certificate of origin, export declaration copy.
Technical
Factory test report (pressure and flow), operation and maintenance manual, parts catalogue with part numbers, wiring diagram, cold-weather commissioning sheet where applicable.
Originals vs scans
Scans the day the truck crosses; originals by courier where the destination customs requires them.
Certification
Certificates as required by the destination market are confirmed case by case before the order is placed — ask early, some take longer than production.
One container, many suppliers — one party answerable for the lot
A drilling spread is rarely one factory. Compressor from one plant, rig from another, hammer and bits from a third, hoses and spares from a fourth. Buy each one direct and you collect four deposits, four export declarations and four arrival dates. We receive them at one address in Chengdu, check them together and load them in the order you will unload them on site.
| Line | Where it comes from | Ships from |
|---|---|---|
| Air compressor | Atlas Copco China plants — Wuxi (compressors), Nanjing (construction & mining) | Chengdu — or ex-works direct |
| Water-well and DTH rig | Xuanhua Jinke, XCMG | Chengdu |
| Hammer, bits, drill pipe, casing | Drilling-tool plants | Chengdu |
| Hoses, adapters, gauges, spare kits | Accessory plants | Chengdu |
| Consumables — hammer oil, grease, wear parts | Mixed | Chengdu |
Coordinated documents
We coordinate the available commercial, packing and transport documents for the quoted equipment package. The exact document set depends on the suppliers, shipment structure and destination requirements.
One inspection day
Every line is checked against the packing list at the same address before the container is sealed, and the photos reach you the same day.
One loading order
The container is packed in reverse of your unloading sequence, so the hammer, hoses and first-day spares come out first at site.
One commercial contact
One commercial contact coordinates the quoted equipment package, documentation and delivery updates. Responsibilities for each item are stated in the quotation; questions about items we do not manufacture are followed up with the supplier on your behalf.
Items we do not make are bought on your behalf and inspected at the same address. If a supplier's lead time slips, you hear it from us before the loading date — not from the port. Mixed loads (LCL) are possible for a small spread; once the spread fills a 40′ HC, a full container is the cheaper route.
Tell us the site and the start date — we will work backwards
Send the destination city and the date the crew must start, and we will return a schedule with the buffer shown.